According to Gary B. Dahl, director of project management at UC Davis Design and Construction Management, there are around 100 projects in planning, design and construction on campus.
Provided below is a list of the major projects in design with estimated cost and completion dates:
January 2013: The Old Davis Road repair, $3 million
End of February 2013: King Hall, $15 million
March 2013: Veterinary Medicine 3B Lab Building, $58 million
April 2013: Jess S. Jackson Sustainable Winery Building, $4 million
Summer 2013: Hutchison Drive relocation, $1 million
December 2013: Respiratory Disease Center, $18 million
August 2014: Tercero Student Housing (Phase 3), $88 million
The following estimated costs and completion dates are for buildings in design:
Designing for Tercero Housing (Phase 4), has already begun
May 2013: UC Davis Welcome Center, $2 million
2015: Seismic retrofits for Olson, Freeborn and Wright Hall, $6 million
March 2015: Music Recital Hall and Classroom building, $15 million
December 2015: International Complex (Phase 1), $27 million
December 2015: South Valley Animal Health Lab, $4 million
May 2016: Jan Shrem and Maria Manetti Shrem Museum of Art, $30 million