UC Davis campus construction update

According to Gary B. Dahl, director of project management at UC Davis Design and Construction Management, there are around 100 projects in planning, design and construction on campus.

Provided below is a list of the major projects in design with estimated cost and completion dates:

January 2013: The Old Davis Road repair, $3 million

End of February 2013: King Hall, $15 million

March 2013: Veterinary Medicine 3B Lab Building, $58 million

April 2013: Jess S. Jackson Sustainable Winery Building, $4 million

Summer 2013: Hutchison Drive relocation, $1 million

December 2013: Respiratory Disease Center, $18 million

August 2014: Tercero Student Housing (Phase 3), $88 million

The following estimated costs and completion dates are for buildings in design:

Designing for Tercero Housing (Phase 4), has already begun

May 2013: UC Davis Welcome Center, $2 million

2015: Seismic retrofits for Olson, Freeborn and Wright Hall, $6 million

March 2015: Music Recital Hall and Classroom building, $15 million

December 2015: International Complex (Phase 1), $27 million

December 2015: South Valley Animal Health Lab, $4 million

May 2016: Jan Shrem and Maria Manetti Shrem Museum of Art, $30 million