According to Gary B. Dahl, director of project management at UC Davis Design and Construction Management, there are around 100 projects in planning, design and construction on campus.
Provided below is a list of the major projects in design with estimated cost and completion dates:
- January 2013: The Old Davis Road repair, $3 million
- End of February 2013: King Hall, $15 million
- March 2013: Veterinary Medicine 3B Lab Building, $58 million
- April 2013: Jess S. Jackson Sustainable Winery Building, $4 million
- Summer 2013: Hutchison Drive relocation, $1 million
- December 2013: Respiratory Disease Center, $18 million
- August 2014: Tercero Student Housing (Phase 3), $88 million
The following estimated costs and completion dates are for buildings in design:
- Designing for Tercero Housing (Phase 4), has already begun
- May 2013: UC Davis Welcome Center, $2 million
- 2015: Seismic retrofits for Olson, Freeborn and Wright Hall, $6 million
- March 2015: Music Recital Hall and Classroom building, $15 million
- December 2015: International Complex (Phase 1), $27 million
- December 2015: South Valley Animal Health Lab, $4 million
- May 2016: Jan Shrem and Maria Manetti Shrem Museum of Art, $30 million